Majuba Project | Nov 2014

Majuba Project | Nov 2014

The Majuba project is progressing well Stallion has supplied approx  28 000 m3 pored to date. The contract is progressing well notwithstanding several strikes and Rainfall delays.

Stallion supply capacity has also been increased by the installation of a second Back to Back batching plant at Rietspruit which can produce up to 66m3 per hour.
Stallion has 3 fully automated Karoo batch plants supplying this project .

Statistics


 

Bridge decks Poured at Km,s

  • 2.5 ; 6.3; 7.3; 8.0 ;8.5;17.15; 18.5 ; 15 ; 26 ; 28 ; 30 ; 33 ; 34 ; 36 ; 38 ; 48; 49; 56; 63; 66
Skills

Posted on

February 26, 2015